Page 1 of 1
ETA on Suite Renovation Completion?

Posted:
Mon Aug 12, 2013 4:07 pm
by DiamondM
I drive by nearly every day, and it just doesn't seem as close to being done, either exterior or interior, as I would expect with less than 3 weeks to go before the season. Are these going to be done by August 30 when we have our biggest crowd of the year on national tv? Please tell me yes.
And if not, please tell me that we negotiated a construction contract with huge delay penalties.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 8:33 am
by Alaric
Time to start having those guys work 24 hours/day. They're going to need the time just to make the place safe - doesn't look like there's any way work will be complete, especially finish out which is always slow.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 9:27 am
by couch 'em
Who is the contractor?
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 11:14 am
by RE Tycoon
We should have vetted them through Angie's List.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 11:23 am
by East Coast Mustang
@AD_RickHart 20h
New outdoor club/suite seats being installed at Ford. Just 18 days until they are filled w/ Pony fans! #SMU #PonyUp pic.twitter.com/C3ufxYsRiu
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 11:41 am
by GRGB
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 12:00 pm
by ALEX LIFESON
August 26.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 12:16 pm
by docabel
***next week***
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 1:44 pm
by lwjr
docabel wrote:***next week***
Done Deal!
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 1:58 pm
by Mustangsabu
I did hear that the contractor asked if the tech game was a day or night game.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 4:18 pm
by DiamondM
Okay, I don't care if the fancy pants suite owners get high on fresh paint fumes and the toilet flushes when you flip the light switch, as long as the are done and look pretty on tv.
Still not sure why we are cutting it so close given they've had almost 9 months to do these.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 6:18 pm
by SMU89
There isnt that much left to do
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 6:49 pm
by smusic 00
Except the complete finish out.
Re: ETA on Suite Renovation Completion?

Posted:
Tue Aug 13, 2013 6:53 pm
by RGV Pony
DiamondM wrote:
Still not sure why we are cutting it so close given they've had almost 9 months to do these.
Ever had a deadline for a contractor /contractors to meet? They are amazingly resourceful in their quest to push and seldom meet the deadline and come in far, far overbudget